November 20, 2018

This week, construction crews are working on finishing pavement markings on Cedar Street. They will also continue to place street lights, work on traffic signals, and install landscaping elements.

It has been decided that Cedar Street will remain one way until the street lights are completed so drivers can see during evening hours. Please keep following the Realize Cedar page for more updates on when the detour will be lifted.

November 16, 2018

Unfortunately, due to the snow we received yesterday and today, the contractors were unable to finish the final topping layer on the west side of Cedar Street as planned. They will work to complete the final paving on Monday or Tuesday and Cedar Street will be open to two-way traffic as soon as they are complete. Thank you for your patience as we accommodate the changing weather.

November 6, 2018

This week, construction crews are working on topping the east side of Cedar Street and finishing up concrete and street lighting work. Next week, they will top the west side of Cedar Street, officially completing the road work associated with the project.

The project is scheduled to be completed on Dec. 14, weather permitting. Between the end of the Cedar Street topping and Dec. 14, there may be intermittent lane closures as construction crews work on replacing street lights, traffic signals, adding benches, etc.

October 30, 2018

This week, construction crews are working on fine-grading and paving the Aurelius/Cedar intersection. Weather permitting, the intersection paving and striping should be completed by early next week. Crews will also continue pouring concrete for the new sidewalks around the intersection.

Next week, crews will finish topping the pavement on Cedar Street between the Holt/Cedar and Aurelius/Cedar intersections. During this time, Cedar Street between Holt and Aurelius will be northbound only to allow crews to finish topping the street.

October 23, 2018

This week, construction crews are working on the Aurelius/Cedar intersection. They are replacing utility lines and storm sewer. Next week, they will grade and pave the road to finish up the intersection within the two-week timeframe. Smaller crews are also finishing up pouring sidewalks and installing landscaping along Cedar Street.

October 2, 2018

This week, construction crews are working on removing old pavement and concrete from Keller Road. Crews are also working on grading the east side of Cedar Street to prep for repavement.

Within the next few weeks paving should begin on the east side of Cedar Street and the Keller Road intersection should be complete.

September 26, 2018

September 26, 2018

This Saturday, construction crews will be working on the southwest corner of the Holt Road and Cedar Street intersection. During this time, eastbound traffic on Holt Road will need to be detoured around the construction zone to accommodate the workers. Please use the same detour as Phase 2, as shown below. Motorists will still be able to travel northbound on Cedar. Thank you for your patience.

August 21, 2018

This week, construction crews finished up work on the Holt/Cedar intersection. The intersection is now open to traffic. Moving forward, they will demolish the sidewalk and mill the pavement on the east side of Cedar Street to continue with the project timeline. Cedar Street is now a northbound only road again. Please follow the same detour as Phase 1.

August 14, 2018

This week, construction crews are finishing up construction on Phase 2 of the project: the Holt/Cedar intersection. So far, they have installed storm sewers, conduit lines for street lighting and traffic signals, and curbed the outside of the intersection for new curb and gutter. They will finish up with paving towards the end of this week. Phase 2 construction is set to be finished by next Monday, weather permitting.

Phase 3, the east side of Cedar Street, is scheduled to begin next week after the conclusion of Phase 2. When Phase 3 begins, Cedar Street will become a northbound only street again. Please follow the original detour from Phase 1.

August 7, 2018

Last week, construction crews finished up Phases 1 and 5 of the Realize Cedar project. This week, crews are working on the Holt/Cedar intersection. Currently, contractors are working on finishing removal of old material and installing new storm sewers. Crews are also working on the signals for the new intersection. This section of the project is scheduled to last for two weeks.

July 24, 2018

This week, crews are continuing to place sidewalks on the west side of Cedar Street, place electrical conduit for street lighting, and preparing to pave the roads.

In addition, work on Phase 5 of the project, from Willoughby to Aurelius Roads, has begun. 

Beginning Thursday, the right lanes of northbound and southbound Cedar Street will be closed for milling and repaving. There may be brief times during this roadwork when business driveways are not accessible. Construction crews will work as quickly as possible to ensure that temporary driveways are put in place, however, please use any available alternate entrances to these businesses, if possible. 

Once milling and repaving are finished in the right lanes, the center three lanes will be closed for reconstruction. During this time, cars will be unable to make left-hand turns into business driveways. 

This phase of the project is projected to last for three weeks. Please find alternate routes, follow posted detours, and drive safely. Continue to follow the Realize Cedar pages for up-to-date information on lane closures and detours.

July 17, 2018

This week, construction crews are laying down new conduit and utility lines, as well as grading, all in preparation for the new sidewalks and roads that will be installed in the coming weeks.

Phase 5 of construction, which includes Cedar Street between Aurelius and Willoughby, will begin next week. Expect lane closures on this section. Follow the Realize Cedar Facebook and Instagram pages for more details.