October 23, 2018

This week, construction crews are working on the Aurelius/Cedar intersection. They are replacing utility lines and storm sewer. Next week, they will grade and pave the road to finish up the intersection within the two-week timeframe. Smaller crews are also finishing up pouring sidewalks and installing landscaping along Cedar Street.