August 14, 2018

This week, construction crews are finishing up construction on Phase 2 of the project: the Holt/Cedar intersection. So far, they have installed storm sewers, conduit lines for street lighting and traffic signals, and curbed the outside of the intersection for new curb and gutter. They will finish up with paving towards the end of this week. Phase 2 construction is set to be finished by next Monday, weather permitting.

Phase 3, the east side of Cedar Street, is scheduled to begin next week after the conclusion of Phase 2. When Phase 3 begins, Cedar Street will become a northbound only street again. Please follow the original detour from Phase 1.