August 7, 2018

Last week, construction crews finished up Phases 1 and 5 of the Realize Cedar project. This week, crews are working on the Holt/Cedar intersection. Currently, contractors are working on finishing removal of old material and installing new storm sewers. Crews are also working on the signals for the new intersection. This section of the project is scheduled to last for two weeks.